<ArticleTitle>Determining Control Points in the Project Life Cycle‎: ‎A Heuristic Approach Utilizing Tabu Search</ArticleTitle>
<VernacularTitle></VernacularTitle>
			<FirstPage>163</FirstPage>
			<LastPage>173</LastPage>
			<ELocationID EIdType="pii">11875</ELocationID>
			
<ELocationID EIdType="doi">10.30473/coam.2025.73812.1290</ELocationID>
			
			<Language>EN</Language>
<AuthorList>
<Author>
					<FirstName>Narjes</FirstName>
					<LastName>Sabeghi</LastName>
<Affiliation>Department of Mathematics‎, ‎Faculty of Basic Sciences‎, ‎Velayat University‎, ‎Iranshahr‎, ‎Iran‎.</Affiliation>

</Author>
</AuthorList>
				<PublicationType>Journal Article</PublicationType>
			<History>
				<PubDate PubStatus="received">
					<Year>2025</Year>
					<Month>02</Month>
					<Day>14</Day>
				</PubDate>
			</History>
		<Abstract>A critical aspect of successful project management is ensuring that execution aligns with the baseline schedule‎. ‎However‎, ‎traditional project control methods often struggle to effectively address the uncertainties and deviations that can arise during project execution‎, ‎leading to delays and inefficiencies‎. ‎To tackle these challenges‎, ‎this paper introduces a novel heuristic approach based on the Tabu Search (TS) algorithm for identifying discrete control points throughout the project life cycle‎. ‎These control points enable proactive monitoring‎, ‎timely deviation detection‎, ‎and corrective actions‎, ‎significantly minimizing project delays‎. ‎Unlike traditional scheduling techniques‎, ‎which can be rigid and reactive‎, ‎our proposed method dynamically adjusts control points to enhance project oversight‎. ‎Experimental results on benchmark instances from the Kolisch library demonstrate that our approach significantly reduces project delays‎, ‎with up to 20% improvements compared to initial schedules in certain scenarios‎. ‎These findings underscore the effectiveness of the TS algorithm in enhancing project control strategies‎, ‎highlighting its potential applicability in real-world project management scenarios‎.</Abstract>
		<ObjectList>
			<Object Type="keyword">
			<Param Name="value">Project management‎</Param>
			</Object>
			<Object Type="keyword">
			<Param Name="value">‎Scheduling‎</Param>
			</Object>
			<Object Type="keyword">
			<Param Name="value">‎Proactive management‎</Param>
			</Object>
			<Object Type="keyword">
			<Param Name="value">‎Control points‎</Param>
			</Object>
			<Object Type="keyword">
			<Param Name="value">‎Tabu search algorithm</Param>